Construction of base slab with TRIO formwork at South Approach Ramp

Tuen Mun - Chek Lap Kok Link Northern Connection Sub-sea Tunnel Section
New Territories , Hong Kong

Tuen Mun – Chek Lap Kok Link (TMCLKL)’s 5km long sub-sea road tunnel is a core component connecting Northwest New Territories (NWNT) with the Hong Kong International Airport (HKIA). The project involves two major reclamation areas, Northern Landfall in Tuen Mun and Southern Landfall adjacent to HKIA.

PERI works closely with DBJV to construct various structures on the two landfalls. On the North, the TRIO panel system is utilized for the ventilation shaft and ventilation building. On the South, various systems are in place to achieve construction efficiency and safety. Bespoke scaffold traveler, wall, and slab formwork travelers are supplied to construct the 250m long cut and cover tunnel.

 

 

Project participants
Customer: Dragages-Bouygues Joint Venture

The Project

Impressions from the project process

Project Information

Related Products

Want to know how PERI can support your project?

We will tailor the most optimal solution to meet your specific requirements.