You are on PERI's international website. Click here to switch to PERI USA. Click here to view all PERI websites.

Hotel Le Royal, Luxembourg

Project data

Location: Luxembourg, Luxembourg

Complete refurbishment of the 5-star Hotel Le Royal in the Luxembourg city centre

Requirements

  • Elaborate core refurbishment in only 9 months 
  • Hotel tract with 165 rooms completely gutted
  • Expansion construction measures on the ground floor prevent erection of facade scaffolding and anchoring to the facade of the hotel
  • Removal of rubble as well as large-sized wall and slab panels through the window opening

Customer

Soludec S.A., Differdange

Customer's benefit

  • One solution for two tasks: safe working platforms for positioning bulk materials containers – large-sized wall and slab panels can be removed through the windows with the help of suspended formwork carriages
  • Both modular construction systems could be combined resulting in a uniform 25-cm system grid and the use of standardized connecting means
  • Time savings and cost benefits due to exclusive use of rentable standard component
Comment from Thomas Bronquard, Foreman, at the PERI project Hotel Royal in Luxembourg with PERI UP, MULTIFLEX and VARIOKIT products.
Thomas Bronquard
Foreman

The great strength of PERI is that system components of different product ranges can be coupled with one another in virtually any combination. Especially for complex and atypical building projects, this is particularly advantageous. The result is reliable and safe solutions – whilst always taking into consideration the economic aspects.

PERI solution

  • Customized project solution on the basis of two compatible PERI modular construction systems: VARIOKIT and PERI UP
  • 8 cantilevered load platforms as generously-dimensioned working and material platforms
  • Suspended scaffolding by means of RCS Rails and Trolley UFS 20 as integrated formwork carriag

 

PERI systems in use